Progress Report - March 2026
Our March progress has been slowed somewhat because of the construction activity being accomplished in bays 1 and 10 at the north end of building 14. 23-003 is in bay 9 which shares a hangar wall with bay 10. The construction has cut electrical power to this wall, but we are working around this problem. Also, our access to bay 9 now involves having to go through a badge access turnstile which limits our volunteers to those of us who have contractor badges.
Even with these construction issues, we are continuing with the cutting and marking of the new wiring for the new wiring harness and tracking parts. Also, the wing that we acquired from 23-024 arrived at building 14 on March 3, 2026. We are using this wing to salvage parts including the leading edges, hydraulic components, etc. that will help with the restoration of 23-003 and needed spares.
We are completing the final leveling of the fuselage and securing the supports. This will allow us to remove damaged fuselage skins. With these skins removed, Non-Destructive Inspections (NDI) can continue in order to provide us additional data on the fuselage structural integrity.
Ed Grabman, Experimental Test Pilot at the Bombardier Flight Test Center, has agreed to chair the 23-003 Cockpit Configuration Committee. This committee is tasked with determining the cockpit upgrades required to operate 23-003 in the current airspace system while maintaining, as much as possible, the look of the original cockpit.
Parts donated by Incora are continuing to arrive with the latest delivery on March 3rd. These much needed, and greatly appreciated, parts include mechanical hardware, aircraft wiring and some electrical components.