Kristen Nuss • September 10, 2025

Progress Report - August 2025

The final sealing of the fuselage, tip tanks and horizontal stabilizer has been completed and they were prepared to be shipped off to have their external paint removed. All openings, seams, windshield and windows had aluminum tape or sealer applied to keep the chemical stripper out of the inside.


The tip tanks and horizontal stabilizer were loaded onto a trailer on August 5, 2025 and taken to a paint facility for paint stripping using Al Goodwin’s truck and a trailer borrowed by Dave Dendurant. The tip tank cradles were the same ones that were used for their trip from Florida.


The fuselage was lifted off of its jacks and placed in its cradle on a trailer for its trip to have the paint stripped on August 12, 2025. The truck and trailer, as well as the trip to the paint facility, were donated by Patton Trucking of Clearwater, Kansas.


These parts should be back in building 14 in early September and ready to have the remaining bits of paint removed. Then we will remove the windshields, windows, panels, finish the internal foam removal and start the Non-Destructive Inspection (NDI). Any issues found on the skins, stringers, etc., such as corrosion, will be repaired or replaced.


While these parts are out to be stripped, we are currently setting up to do a pressure check of the right hand wing looking for any leaks. These results, along with the corrosion found on the left wing, will help us make a decision about the wing. Whether it is repairable or we must replace it. Cross your fingers!


We just passed 1,400 volunteer hours since 23-003 arrived in Wichita! Thank you to all of you who have contributed your time to help restore 23-003!

Read the full newsletter by clicking the button below.

Download Full Newsletter
By Kristen Nuss May 1, 2026
April was a historic month in the restoration of 23-003 N200Y!! First, on April 14 th , after final leveling, the fuselage cradles, jacks and supports were secured firmly to the hangar floor with a special plaster mixture containing hemp fibers (some ropes are made with these fibers). This plaster mixture is commonly used on the factory floor to set tooling jigs so that they cannot move ensuring accurately produced parts and assemblies. With the fuselage secured, we were able to start the removal of skins from the fuselage that need replacement or repair. On April 21, 2026 Hartney Hummer removed the 1st skin panel!! This panel is on the left side of the fuselage, just aft of the engine pylon. This particular panel is not repairable and will have to be replaced. Removal of this panel will also allow the non-destructive inspections (NDI) of the aft fuselage to continue. The NDI test equipment is too big to fit inside the aft fuselage so it will be positioned outside of the stringers pointing inside. International Turbine Industries (ITI) has started the restoration of our CJ610-1 engines. The inspection of the engine cases has started in preparation for them being shipped out to have a coating applied. During earlier discussions between ITI and CLJF, we decided that during the restoration, the engines will be upgraded to the ‘dash 4’ (CJ610-4) configuration. The CJ610-4 engine is a previously approved FAA configuration for the Model 23.
By Kristen Nuss April 1, 2026
Our March progress has been slowed somewhat because of the construction activity being accomplished in bays 1 and 10 at the north end of building 14. 23-003 is in bay 9 which shares a hangar wall with bay 10. The construction has cut electrical power to this wall, but we are working around this problem. Also, our access to bay 9 now involves having to go through a badge access turnstile which limits our volunteers to those of us who have contractor badges. Even with these construction issues, we are continuing with the cutting and marking of the new wiring for the new wiring harness and tracking parts. Also, the wing that we acquired from 23-024 arrived at building 14 on March 3, 2026. We are using this wing to salvage parts including the leading edges, hydraulic components, etc. that will help with the restoration of 23-003 and needed spares. We are completing the final leveling of the fuselage and securing the supports. This will allow us to remove damaged fuselage skins. With these skins removed, Non-Destructive Inspections (NDI) can continue in order to provide us additional data on the fuselage structural integrity. Ed Grabman, Experimental Test Pilot at the Bombardier Flight Test Center, has agreed to chair the 23-003 Cockpit Configuration Committee. This committee is tasked with determining the cockpit upgrades required to operate 23-003 in the current airspace system while maintaining, as much as possible, the look of the original cockpit. Parts donated by Incora are continuing to arrive with the latest delivery on March 3rd. These much needed, and greatly appreciated, parts include mechanical hardware, aircraft wiring and some electrical components.
By Kristen Nuss March 3, 2026
The tip tanks and keel beam are back in Florida!! S.E.A.L. Aviation has generously volunteered to rebuild and restore our tip tanks and keel beam! Since they are in southern Florida, we loaded them up in a truck for the trip back to Florida. Ron Forshee and Chris Marshall volunteered to make the long drive. They departed Wichita on February 15 th at 12:35 pm and arrived in Florida at the Global Jetcare hangar two days and 1,306 miles later on February 17th. The tip tanks and keel beam will now be taken to the S.E.A.L. facility for restoration. A volunteer has started cleaning the flight controls, ailerons, flaps, etc., so that we can accomplish the necessary detailed inspections. As you can see in the photo below, they are quite dirty after sitting outdoors for years. Volunteers Dan DeMott and Cliff Ives are identifying all of the hydraulic and fuel tubes and components that have been removed from 23-003 with part numbers and Parts Catalog locations. The tubes will also have metal ID tags to facilitate vapor degreasing when the time comes for this operation.  Another milestone was reached late this month in the restoration of 23-003: The fuselage has been firmly tied down, securing it to prevent any movement. This will allow us to now start the necessary structural repairs! In the photos below you can see the cradles and supports securing the fuselage. One cradle just forward of the cabin door, a cradle aft of the cabin window, the jacks on the engine beams, a cradle just aft of the engine pylon and the tail stand.