Kristen Nuss • December 5, 2025

Progress Report - November 2025

With the removal of the windshields, glareshield and remaining instrument panel framework, we now have access to the foam insulation around the forward pressure bulkhead and the most forward fuselage. Ryan Timesch, owner of Best Engineered Performance Coatings (BEPC), and his daughter Raegan, came out on November 14 and 15, 2025 to finish their removal of foam beneath the cockpit floor and these now exposed areas in the forward fuselage.


Following completion of the interior foam removal, the fuselage was moved to the north side of the hangar where it will be prepared for the Non-Destructive Inspections (NDI). It will be secured so that, after the NDI, any defective fuselage structure that is found can be repaired or replaced safely without allowing the fuselage to move or twist. The wing was moved to the south side of the hangar.


Visitors, November 2025


Shane Johnson and family came out on Friday, November 15, 2025, to witness the dry ice blasting first hand. They were impressed at how easily and completely the dry ice removed the fuselage foam. They were able to see the before and after effects of the dry ice.


The latest Flight Safety International (FSI) Model 45 training class visited 23-003 on November 6, 2025. Rick Rowe, CLJF Director of Public Relations, and Ron Forshee, CLJF Board member, provided the tour for the class and their instructors Abe Vidulich and Phil Heseltine.

Read the full newsletter by clicking the button below.

Download Full Newsletter
By Kristen Nuss April 1, 2026
Our March progress has been slowed somewhat because of the construction activity being accomplished in bays 1 and 10 at the north end of building 14. 23-003 is in bay 9 which shares a hangar wall with bay 10. The construction has cut electrical power to this wall, but we are working around this problem. Also, our access to bay 9 now involves having to go through a badge access turnstile which limits our volunteers to those of us who have contractor badges. Even with these construction issues, we are continuing with the cutting and marking of the new wiring for the new wiring harness and tracking parts. Also, the wing that we acquired from 23-024 arrived at building 14 on March 3, 2026. We are using this wing to salvage parts including the leading edges, hydraulic components, etc. that will help with the restoration of 23-003 and needed spares. We are completing the final leveling of the fuselage and securing the supports. This will allow us to remove damaged fuselage skins. With these skins removed, Non-Destructive Inspections (NDI) can continue in order to provide us additional data on the fuselage structural integrity. Ed Grabman, Experimental Test Pilot at the Bombardier Flight Test Center, has agreed to chair the 23-003 Cockpit Configuration Committee. This committee is tasked with determining the cockpit upgrades required to operate 23-003 in the current airspace system while maintaining, as much as possible, the look of the original cockpit. Parts donated by Incora are continuing to arrive with the latest delivery on March 3rd. These much needed, and greatly appreciated, parts include mechanical hardware, aircraft wiring and some electrical components.
By Kristen Nuss March 3, 2026
The tip tanks and keel beam are back in Florida!! S.E.A.L. Aviation has generously volunteered to rebuild and restore our tip tanks and keel beam! Since they are in southern Florida, we loaded them up in a truck for the trip back to Florida. Ron Forshee and Chris Marshall volunteered to make the long drive. They departed Wichita on February 15 th at 12:35 pm and arrived in Florida at the Global Jetcare hangar two days and 1,306 miles later on February 17th. The tip tanks and keel beam will now be taken to the S.E.A.L. facility for restoration. A volunteer has started cleaning the flight controls, ailerons, flaps, etc., so that we can accomplish the necessary detailed inspections. As you can see in the photo below, they are quite dirty after sitting outdoors for years. Volunteers Dan DeMott and Cliff Ives are identifying all of the hydraulic and fuel tubes and components that have been removed from 23-003 with part numbers and Parts Catalog locations. The tubes will also have metal ID tags to facilitate vapor degreasing when the time comes for this operation.  Another milestone was reached late this month in the restoration of 23-003: The fuselage has been firmly tied down, securing it to prevent any movement. This will allow us to now start the necessary structural repairs! In the photos below you can see the cradles and supports securing the fuselage. One cradle just forward of the cabin door, a cradle aft of the cabin window, the jacks on the engine beams, a cradle just aft of the engine pylon and the tail stand.
By Kristen Nuss February 2, 2026
LATE BREAKING NEWS: The rebuilding of 23-003 N200Y has officially started! On January 28, 2026 the first set of wires for the new wire harness were cut! Volunteers Denver Plumb and Mike Johnson made the first cut! We would like to thank John Bowman and Larry Thimmesch of Incora for the donation of the wire. We are making great progress in getting all the removed parts identified with part numbers and returned to the storage racks. We are working with Katie Yaverski to get all the racks identified and labeled for location identification. We are moving forward with a partnership with S.E.A.L. Aviation for overhaul and repair of numerous items and components! They will be a great asset to CLJF and the efforts to rebuild 23-003. The wing from of 23-003 is now in a stored position on its leading edge against the south hangar wall in order to give us some additional working room in the hangar.